Time Frame

 Fibre Rollout Forecast

The original (2011-13)  NBN Co Corporate Plan assumed that the rollout would be completed by December 2020 (9.5 years from July 2011). As a result of the delay of the Commencement Date of the Telstra Definitive Agreement from June 2011 to March 2012 there was a corresponding delay in the commencement of the volume rollout.

The 2012-15 NBN Corporate Plan  forecasts that 13 million premises will be passed or covered by NBN Co by the end of Financial Year 2021 (100% of premises across all networks). By the end of Financial Year 2015, NBN Co forecasts passing or covering 3.7 million premises, of which 2.9 million will be with Fibre.

The table below gives the NBN Co schedule  of the premises passes and connected.

Financial Year Premises Passed
(1000’s)
Premises Connected
(1000’s)
2011 18 1
2012 39 4
2013 341 54
2014 1,307 487
2015 2,912 1,515
2016 4,625 3,036
2017 6,279 4,341
2018 7,838 5,594
2019 9,283 6,695
2020 10,783 7,607
2021 12,202 8,513

The Transit Network

NBN Co currently estimates that the Transit network will be completed in Financial Year 2015.  This involves the following:

  • The deployment of Fibre connectivity of transit network
  • 121 Points of Interconnect (PoIs)
  • More than 650 Fibre Access Nodes (FANs)

The remaining FANs, being estimated at more than 400, to be built over the FY2016 – FY2021  period)